Please visit Jefferson Lab Event Policies and Guidance before planning your next event: https://www.jlab.org/conference_planning.

SC1R Installation Review Meeting

US/Eastern
room 101 (building 87)

room 101

building 87

Dana Arenius (Jefferson Lab) , Dave Kashy (JLab) , Jonathan Creel (Jefferson Lab) , Matthew Howell (ORNL) , Steve Suhring (Jefferson Lab) , Tim Whitlatch (Jefferson Lab)
SC1R IR Final Charge
    • 8:30 AM 8:50 AM
      Introduction

      a. Outline
      b. Charge
      c. Design Status
      d. Critical Components Status
      e. Fabrication Status
      f. FDR Recommendations
      g. Traveler

      Convener: Kelly Dixon (Jefferson Lab)
      slides
    • 8:50 AM 9:10 AM
      Insulation Overview

      a. Insulation on internal piping spools
      b. Insulation on CC casings
      c. Insulation on Top Torispherical head
      d. Insulation on vacuum vessel shell
      e. Insulation on internal frame and HX

      Convener: Mr Nate Laverdure (Jefferson Lab)
      slides
    • 9:10 AM 9:40 AM
      SC1R 2K Cold Box Rigging Overview & Platform

      a. Platform review
      b. Building modification requirements
      c. Removal of the existing 2K cold box
      d. SC1R 2K cold box installation plan
      e. Safety

      Convener: Thomas Renzo (Jefferson Lab)
      slides
    • 9:40 AM 10:00 AM
      U-tubes and other auxiliary piping installation
      Convener: Mr Corey Butler (Mechanical Designer Jefferson Lab)
      slides
    • 10:00 AM 10:10 AM
      Break #1 10m
    • 10:10 AM 10:30 AM
      Instrumentation, Controls, and Electrical Support
      Convener: Mr Robert Norton (Jefferson Lab)
      slides
    • 10:30 AM 10:50 AM
      Safety-Fabrication, Assembly, and installation
      Convener: Mr Nate Laverdure (Jefferson Lab)
      slides
    • 10:50 AM 11:20 AM
      SC1 Demo and SC1R Installation Schedule Overview
      Convener: Shirley Yang (JLab)
      document
    • 11:20 AM 11:40 AM
      Discussion

      All

    • 11:40 AM 2:30 PM
      Break #2 + Lunch 2h 50m
    • 2:30 PM 3:00 PM
      Review Committee Report Draft
      Convener: Dave Kashy (JLab)